Case study / Linden Grove kitchen

Opening a 1974 kitchen to the dining room.

A closed galley kitchen with an 11 ft 4 in bearing wall between it and the dining room. The owners wanted one room, an island and no beam hanging below the ceiling.

House
1974 split-level
Area
286 sq ft combined
Contract
$96,400 fixed
Change orders
1, +$2,150
Schedule
38 of 40 days
Crew lead
Mark Lindqvist
Finished open kitchen with a gray island, white counters and three pendants

Sheet P-102 / Sequence

Day by day

Drag along the strip to step through the job. Days are working days, Monday to Friday.

Room stripped to the studs with temporary shoring posts
Wall opening with the new beam, shoring and a worker on a ladder
New supply and drain lines inside an open wall
Open wall framing with new electrical boxes and wiring
Drywall sheets stacked in a framed room
New white base cabinets wrapped in protective plastic
Installer cutting porcelain tile on a work bench
Carpenter caulking window trim in the new kitchen
Finished open kitchen with a gray island

Day 1

Protection and demo

Floors covered, dust wall with a zip door, negative air running. Old cabinets and plaster out. Temporary shoring set on both sides of the wall.

Day 4

Beam in

Two-ply 1-3/4 x 11-7/8 in LVL set flush in the ceiling joists on hangers. New posts carried to the footing. Engineer's letter on site.

Day 9

Plumbing rough-in

Sink moved 6 ft to the island. Drain sloped at 1/4 in per foot, island vented with a loop vent under the sink cabinet. Rough plumbing inspection passed.

Day 11

Electrical rough-in

Two 20 amp countertop circuits, an island circuit, a dedicated range circuit and 14 recessed lights. Electrical and framing inspections passed.

Day 16

Insulation and drywall

Exterior wall insulated and sealed. Drywall hung, taped and finished to level 4, then primed.

Day 22

Cabinets set

Cabinets set level within 1/16 in over the 14 ft run. Counters templated the same afternoon.

Day 29

Counters and tile

Quartz installed on day 27. Backsplash tile laid from the range centerline, so both ends finish on matching cuts.

Day 34

Trim and punch list

Window casing, crown, toe kicks and panel ends. Appliances in and tested. Final inspection on day 36.

Day 38

Walkthrough

Punch list of 11 items closed. Closeout binder handed over with paint codes, manuals and the warranty.

Inspections: rough plumbing day 9, electrical and framing day 11, final day 36.

Sheet P-103 / Comparison

Before and after

Drag the line, or tab to it and use the arrow keys.

Finished kitchen with a gray island and white upper cabinetsAfter / day 38
Kitchen space stripped to bare floor and walls during demolitionBefore / week 1
Drag to compare the kitchen before and after
The island sits where the old wall stood. The beam is hidden in the ceiling plane.

Sheet P-104 / Walkthrough

The wall, in 20 seconds

A short cut of the job photos, from the shoring on day 1 to the handover on day 38, with captions.

Wall opening with temporary shoring and a worker on a ladder

Removing a bearing wall, start to finish

Silent, with captions.

In this video

What Karen wrote afterwards

We wanted the wall between the kitchen and dining room gone without a beam hanging down, and they put in a flush beam you honestly cannot see. The drawings showed every outlet before demo. Done in 38 working days, they had said 40. Final bill was the contract plus the one change order we asked for (pantry pull-outs, worth it).

Karen L.Linden GroveKitchen, bearing wall removed